After months of preparation, design, testing, and training, it’s time to bring your solution to life. The Deploy and Run Phases of SAP Activate mark the beginning of production use and the shift toward sustainable operations and continuous value realization.
The Deploy Phase — Executing Go-Live with Precision
The Deploy Phase culminates the project’s pre-production efforts and executes the transition from legacy systems to SAP S/4HANA Cloud. It is a high-focus, time-bound phase, where every detail matters.
Cutover Planning and Execution
Cutover refers to the series of coordinated activities that transition your system from test to production.
- Final data load and validation
- Business continuity planning during the transition
- Communication plans for users and stakeholders
- Freeze periods and system switchover timelines
A successful cutover requires strict execution of a well-documented runbook and full involvement from IT, business, and support teams.
Transitioning to Steady-State Operations
Once the system is live, the focus moves to ensuring system stability and user support.
- Establish a Hypercare period: short-term intensive support with rapid issue resolution
- Activate support channels: help desk, super users, and escalation paths
- Monitor KPIs for performance, adoption, and issue tracking
Hypercare isn’t just technical—it includes user confidence, operational consistency, and quick turnaround on post-go-live refinements.
The Run Phase – Continuous Improvement in the Cloud
S/4HANA Cloud is built for innovation. Post-go-live, the real journey begins—adapting to changing needs, adopting innovations, and maximizing ROI.
Realizing Value through Key Metrics
To ensure you’re meeting your transformation goals, track both technical and business metrics:
- Adoption metrics (user activity, transaction volumes)
- Performance indicators (order processing time, automation rates)
- Value realization (cost savings, process efficiency)
Use tools like SAP Analytics Cloud to visualize performance and track value against your original business case.
Embracing Upgrade Release Cycles
SAP S/4HANA Cloud delivers bi-annual innovations and upgrades (Feb & Aug). The Run Phase includes preparing your systems and users to absorb these changes seamlessly.
- Review upcoming release content in SAP Roadmap Viewer
- Conduct impact assessments for business processes
- Train key users on new capabilities
- Leverage SAP Cloud ALM for change control and documentation
Establish a release governance model to manage innovation without disrupting operations.
Deliverables of Deploy & Run Phases
- Completed production cutover and go-live communication
- Stabilized system through Hypercare with documented learnings
- Active support channels and knowledge base for end-users
- Defined operational KPIs and value realization tracking
- Governance structure for managing quarterly updates
Final Takeaway: Go-Live Is Just the Beginning
The Deploy and Run Phases signal the start of your organization’s digital evolution—not the end. With the right structure in place, S/4HANA Cloud becomes a platform for agility, insight, and continuous innovation.
This is the sixth and final step in our SAP Activate series, where we walk you through the full lifecycle of S/4HANA Cloud implementation, step by step. Stay tuned for our next and final post, recapping the full series.